Northern Natural Gas Company

Original Volume No. 2

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 01/22/2000, Docket: CP00- 20-001, Status: Effective

Fourth Revised Sheet No. 458 Fourth Revised Sheet No. 458 : Effective

Superseding: Third Revised Sheet No. 458

 

 

 

 

 

CANCELLATION OF RATE SCHEDULE T-8

 

Notice is hereby given that effective December 9, 1999, the

Gas Transportation Agreement between Northern Natural Gas Company

and Reliant Energy Minnegasco, successor in interest to

Minnegasco, Inc., dated August 19, 1983, and relating to service

under Rate Schedule T-8 on Third Revised Sheet Nos. 458-459,

Second Revised Sheet No. 460, First Revised Sheet Nos. 461-462,

Eleventh Revised Sheet No. 463, First Revised Sheet No. 464 and

Original Sheet Nos. 464a-464m, is to be cancelled pursuant to the

Commission's Order issued December 9, 1999 whereby Northern was

granted permission for and approval of the abandonment of service

in Docket No. CP00-20-000.