83 Revised Sheet No. 53 83 Revised Sheet No. 53

Superseding: 82 Revised Sheet No. 53

 

Commodity

Charges

----------

Nov-Oct

-------

GS-T COMMODITY THROUGHPUT RATE

Market Area 0.7049 1/ 6/

Field to Demarcation 0.6396

Field-to-Market 1.2606 1/ 6/

 

STAND ALONE COMPRESSION

 

Ft. Buford

Maximum 0.2619 1/ 2/ 6/

Minimum 0.0125 1/ 2/ 6/

 

RATE SCHEDULE CS-1

 

Compression Fee (Exhibit A Volumes)

Maximum 0.0401

Minimum 0.0054

 

Compression Fee (Additional Volumes)

Maximum 0.0401

Minimum 0.0054

 

BEAVER COMPRESSION FEE

 

Incidental Jurisdictional Compression Fee 0.0400

 

WATERVILLE STORAGE

 

The Market Area transportation rate, fuel and unaccounted for is charged for delivery

to Waterville storage point (POI 922), or other similarly situated third party storage

points in the Market Area. If redelivery from Waterville, or other similarly situated

third party storage points, is to a Market Area point, there are no additional

transportation, fuel or unaccounted for charges. If the redelivery is to a Field Area

delivery point, the Field Area mileage/MID transportation rate and fuel is charged.

 

CAPACITY RELEASE FEE (Rate per transaction)

Marketing Negotiated 3/

 

DAILY DELIVERY VARIANCE CHARGE:

Positive DDVC 1.0000 7/

Positive/Critical DDVC

-First 2% 15.0000

-Next 3% 22.0000

Negative DDVC 0.4000 7/

Punitive DDVC 4/ 7/

Punitive/Critical DDVC

-Level I 56.5000

-Level II 113.0000

 

AUTHORIZED OVERRUN

TF, TFX, LFT, TI and GS-T Rate Schedules 5/

 

1/ Includes ACA of $0.0019.

2/ Rate only applies to interruptible volumes transported through Ft. Buford

that are not ultimately confirmed for redelivery into Northern's Market Area

system.

3/ Northern will assess fee only in those instances outlined in Sheet No. 288.

4/ Charge equal to five (5) times the SMS monthly reservation fee.

5/ The Authorized Overrun Rate shall be equal to the TI rate for the applicable

MID path shown in Sheet Nos. 59-60A.

6/ Reflects Market Area Electric Compression Surcharge of $0.0006 and Field

Area Electric Compression charge of $0.0000 where applicable.

7/ On non-SOL/SUL/Critical Days the rate will be the maximum November-March

Market Area TI Rate during the November-March period, and the maximum

April-October Market Area TI Rate during the April-October period.