GENERAL TERMS AND CONDITIONS
10. NOMINATIONS/CONFIRMATIONS/SCHEDULING/INTERRUPTION OF SERVICE
(Continued)
10.4 Capacity Allocation and Confirmation Process (Continued)
10.45 Initiation of Confirmation
The receiver of a nomination initiates the
confirmation process. The party that would receive
a Request for Confirmation or an unsolicited
Confirmation Response may waive the obligation for
the sender to send. [1.3.20]
For request to confirm and confirmation response
processes, all parties will seek to confirm by means
of communicating at the applicable detail/summary
level all transactions with respect to a location.
[1.3.35]