GENERAL TERMS AND CONDITIONS

 

 

10. NOMINATIONS/CONFIRMATIONS/SCHEDULING/INTERRUPTION OF SERVICE

(Continued)

 

10.4 Capacity Allocation and Confirmation Process (Continued)

 

10.45 Initiation of Confirmation

 

The receiver of a nomination initiates the

confirmation process. The party that would receive

a Request for Confirmation or an unsolicited

Confirmation Response may waive the obligation for

the sender to send. [1.3.20]

 

For request to confirm and confirmation response

processes, all parties will seek to confirm by means

of communicating at the applicable detail/summary

level all transactions with respect to a location.

[1.3.35]