Northern Border Pipeline Company

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/01/1998, Docket: RP98-399-001, Status: Effective

Sub First Revised Sheet Number 248J Sub First Revised Sheet Number 248J : Effective

Superseding: Original Sheet Number 248J

 

GENERAL TERMS AND CONDITIONS

 

 

10. NOMINATIONS/CONFIRMATIONS/SCHEDULING/INTERRUPTION OF SERVICE

(Continued)

 

10.2 Nomination and Scheduling Timeline (Continued)

 

10.24 Intra-day 2 Nomination Cycle (Continued)

 

(f) Scheduled Intra-day 2 Nominations Quantity

Summary - Affected Interconnected Party/Point

Operator

 

Company shall provide an affected

Interconnected Party/Point Operator a scheduled

quantity summary by 9:00 p.m. CCT on the Gas

Day.

 

10.25 Emergency Intra-day Requests

 

A majority of the time period in which an emergency

intra-day request can be submitted to Company is

during non-traditional business hours.

Consequently, it is the responsibility of the

Nominating Party to see that Company has been

notified that an emergency intra-day nomination has

been transmitted.

 

Emergency intra-day requests will be processed using

first come, first served, and will be confirmed and

scheduled, if capacity is available on Company's

system, on a best efforts basis.

 

If an emergency intra-day request can be accepted

and processed, Company will produce a quick response

on a timely basis.

 

Scheduled quantity summaries reflecting scheduled

emergency intra-day requests will be generated and

delivered to the appropriate parties on a timely

basis.