Northern Border Pipeline Company

First Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 10/29/2001, Docket: RP01-614-000, Status: Effective

Second Revised Sheet No. 224 Second Revised Sheet No. 224 : Effective

Superseding: First Revised Sheet No. 224

 

GENERAL TERMS AND CONDITIONS

 

 

2. PRESSURE AND TEMPERATURE

 

2.1 Receipt Pressure

 

Shipper shall deliver gas to Company at each of Shipper's

Points of Receipt at a pressure sufficient to cause such

gas to flow into Company's facilities, provided that

Shipper shall not be required to deliver gas to Company at

any Point of Receipt at a pressure in excess of the Maximum

Pressure specified with respect to such Point of Receipt.

 

2.2 Delivery Pressure

 

Company shall deliver gas to Shipper at each of Shipper's

Points of Delivery at the pressure existing in Company's

pipeline at such Point of Delivery, provided that Shipper

shall not be required to receive gas from Company at any

Point of Delivery at a pressure less than the Minimum

Pressure specified with respect to such Point of Delivery.

 

2.3 Maximum Receipt Temperature

 

The temperature of gas delivered by Shipper to Company at a

Point of Receipt shall not exceed the Maximum Receipt

Temperature of 120 degrees F.

 

2.4 Minimum Delivery Temperature

 

The temperature of gas delivered by Company to Shipper at a

Point of Delivery shall not be below the Minimum Delivery