5. INSPECTION OF EQUIPMENT AND RECORDS (Continued)
5.2 (Continued)
In accordance with NAESB Standard 2.3.14, Version 1.8, measurement
data corrections should be processed within six (6) months of the
production month with a three-month rebuttal period. This standard
shall not apply in the case of deliberate omission or
misrepresentation or mutual mistake of fact. Parties' other
statutory or contractual rights shall not otherwise be diminished
by this standard.