Mojave Pipeline Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 03/22/2010, Docket: RP10-330-000, Status: Effective
Second Revised Sheet No. 436 Second Revised Sheet No. 436
Superseding: First Revised Sheet No. 436
FORM OF SERVICE AGREEMEENT
APPLICABLE TO FIRM TRANSPORTATION SERVICE
UNDER RATE SCHEDULE FT-1
(Continued)
EXHIBIT A
TO SERVICE AGREEMENT
UNDER RATE SCHEDULE FT-1
The following data elements shall be described on this Exhibit A, if
applicable:
Points of Receipt 1/
Points of Delivery
Effective Dates
Receipt Quantity 2/
Delivery Quantity 3/
Maximum Daily Quantity
Receipt Pressure 4/
Delivery Pressure 5/
Total
1/ Each point of receipt quantity may be increased by an amount equal to
Transporter's fuel reimbursement percentage. Shipper shall be responsible
for providing such fuel reimbursement at each point of receipt on a pro
rata basis based on the quantities received on any day at a point of
receipt divided by the total quantity delivered at all point(s) of delivery
under this Agreement.
2/ The sum of the receipt quantities at point(s) of receipt shall be equal to
Shipper's Maximum Daily Quantity.
3/ The sum of the delivery quantities at point(s) of delivery shall be equal
to Shipper's Maximum Daily Quantity.
4/ Necessary pressure to enter Transporter's system and, except as otherwise
noted, not in excess of any pressure specified above.
5/ Unless otherwise specified, the Delivery Pressure(s) for the point(s)
listed above shall be the pressure existing from time to time at the
metering facility; however, Transporter reserves the right to deliver
quantities at the pressures up to the MAOP of that facility.