8. Operating Provisions
(c) Flexible Delivery Points: Any Shipper may designate a Secondary
delivery point for receipt of gas from Transporter, subject to the
availability of capacity to and at that delivery point.
Notwithstanding the priorities described in Section 6 of the
General Terms and Conditions, in the event that there is inadequate
capacity for Transporter to make all deliveries scheduled to and at
a delivery point, capacity at that delivery point shall be
allocated as follows:
(i) First, capacity shall be allocated to all Shippers under
Rate Schedule FT-1 for whom such delivery point is a Primary
delivery point and who are transporting gas from a Primary
receipt point.
(ii) Second, capacity shall be allocated to all Shippers under
Rate Schedule FT-1 for whom such delivery point is a
Secondary delivery point and such point is within the
primary path of the receipt and delivery points listed in
the Shipper's Service Agreement.
(iii) Third, capacity shall be allocated to all Shippers under
Rate Schedule FT-1 for whom such delivery point is a
Secondary delivery point and such point is outside the
primary path of the receipt and delivery points in the
Shipper's Service Agreement.
(iv) Fourth, capacity shall be allocated to all Shippers under
Rate Schedule IT-1 for whom such delivery point is a Primary
delivery point and who are transporting gas from a Primary
receipt point.
(v) Fifth, capacity shall be allocated to all Shippers under
Rate Schedule IT-1 for whom such delivery point is a
Secondary delivery point and who are transporting gas from a
Primary receipt point.
(vi) Sixth, capacity shall be allocated to all shippers under
Rate Schedule IT-1 for whom such delivery point is a Primary
delivery point and who are transporting gas from a Secondary
receipt point.
(vii) Last, capacity shall be allocated to all shippers under Rate
Schedule IT-1 for whom such delivery point is a Secondary
delivery point and who are transporting gas from a Secondary
receipt point.
(viii)In the event that there is inadequate capacity to serve all
Shippers to and at a delivery point within any one of the
categories described above, scheduling of those Shippers
shall be in accordance with Section 6 of the General Terms