8. Operating Provisions
8.1(a) Primary and Secondary Receipt and Delivery Points: The receipt
points listed in the Service Agreement of each Shipper shall be
deemed that Shipper's Primary receipt points. The sum of
contracted receipt point quantities shall be equal to shipper's
Maximum Daily Quantity. All other of Transporter's receipt
points shall be deemed that Shipper's Secondary receipt points.
The delivery points listed in the Service Agreement of each
Shipper shall be deemed that Shipper's Primary delivery points.
The sum of contracted delivery point quantities shall be equal to
shipper's Maximum Daily Quantity. All other of Transporter's
delivery points shall be deemed that Shipper's Secondary delivery
points.
(b) Flexible Receipt Points: Any Shipper may designate a Secondary
receipt point for delivery of gas to Transporter, subject to the
availability of capacity at and from that receipt point.
Notwithstanding the priorities described in Section 6 of the
General Terms and Conditions, in the event that there is
inadequate capacity for Transporter to receive all deliveries
scheduled at a receipt point, capacity at and from that receipt
point shall be allocated as follows:
(i) First, capacity shall be allocated to all Shippers under
Rate Schedule FT-1 for whom such receipt point is a Primary
receipt point.
(ii) Second, capacity shall be allocated to all Shippers under
Rate Schedule FT-1 for whom such receipt point is a
Secondary receipt point and such point is within the primary
path of the receipt and delivery points listed in the
Shipper's Service Agreement.
(iii) Third, capacity shall be allocated to all Shippers under
Rate Schedule FT-1 for whom such receipt point is a
Secondary receipt point and such point is outside the
primary path of the receipt and delivery points listed in
the Shipper's Service Agreement.
(iv) Fourth, capacity shall be allocated to all Shippers under
Rate Schedule IT-1 for whom such receipt point is a Primary
receipt point.
(v) Last, capacity shall be allocated to all Shippers under Rate
Schedule IT-1 for whom such receipt point is a Secondary
receipt point.
(vi) In the event that there is inadequate capacity to serve all
Shippers at and from a receipt point within any one of the
categories described above, scheduling of those Shippers
shall be in accordance with Section 6 of the General Terms
and Conditions.