RATE SCHEDULE IT-1
Interruptible Transportation Service
(Continued)
10. Unauthorized Overrun Gas
Unauthorized Overrun Gas shall be the quantity either delivered to or
taken from Transporter's Facilities by Shipper on any day that exceeds
the sum of: (1) Shipper's Daily Quantity; (2) Authorized Overrun Gas;
(3) the quantity of interruptible transportation service provided by
Transporter to Shipper under Rate Schedule IT-1; (4) quantities furnished
by Shipper in-kind for fuel and L&U; (5) imbalance quantities within the
operating tolerances specified in Section 11 of the General Terms and
Conditions; and (6) quantities necessary for Transporter or Shipper to
make up prior imbalances.
10.1 Critical Period Unauthorized Overruns - During a Critical Period,
Shipper shall pay Transporter for Unauthorized Overrun Gas at a
rate equal to two times the maximum Rate Schedule IT-1 rate. Such
payment shall be in addition to all other charges payable by
Shipper to Transporter under this Rate Schedule.
10.2 Non-Critical Period Unauthorized Overruns - During a non-Critical
Period, Shipper shall pay Transporter for Unauthorized Overrun Gas
at a rate equal to the maximum Rate Schedule IT-1 rate. Such
payment shall be in addition to all other charges payable by
Shipper to Transporter under this Rate Schedule.
11. General Terms and Conditions
All the General Terms and Conditions for this Tariff are applicable to