35. SEGMENTATION OF CAPACITY (Continued)
which its Primary or Secondary Receipt Point(s), as applicable, is located,
from that Primary or Secondary Receipt Point(s), as applicable, to the
boundary of MRT's Reticulated System. For purposes of segmentation under this
Section 35, there is no right to a Primary or Secondary Path or Path Segment
within MRT's Reticulated System.
35.6 In all cases, including those situations previously described in
this Section 35, MRT reserves the right to evaluate and disallow segmentation
on its system on a case-by-case basis for those situations that are not
operationally feasible. Disallowance of segmentation requests will be made on
a not unduly discriminatory basis.
36. THIRD PARTY PIPELINE CAPACITY
36.1 MRT, from time to time, may contract in its own name to acquire
and utilize capacity on a third-party system. Any services provided to
Customers using such capacity shall be provided pursuant and subject to the
applicable provisions of MRT's tariff, including the applicable rates, as on
file and in effect from time to time. The "shipper must have title" policy
is waived to permit MRT to utilize such capacity to provide services to its