14. CAPACITY RELEASE (Continued)
14.11 Release by Replacement Customers
All Replacement Customers may re-release their capacity subject to the
terms and conditions for release as set forth herein and, for segmented
releases, in Section 35 of these General Terms and Conditions.
14.12 Release of Firm Storage Service
(a) Any Releasing Customer shall be permitted to release its firm
storage capacity under Rate Schedule FSS utilizing the procedures set forth
in this Section 14. All Pre-Arranged Replacement Customers and Winning
Bidders for such capacity shall be subject to the terms and conditions of
Rate Schedule FSS.