Centerpoint Energy - Mississippi River
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/01/2003, Docket: RP03-466-000, Status: Effective
First Revised Sheet No. 166A First Revised Sheet No. 166A : Effective
Superseding: Original Sheet No. 166A
GENERAL TERMS AND CONDITIONS
(Continued)
14. CAPACITY RELEASE (Continued)
(A) Timely Recall Notification:
(1) A Releasing Customer recalling capacity
must provide notice of such recall to MRT
and the first Replacement Customer no
later than 8:00 a.m. on the day that
Timely Nominations are due;
(2) MRT will provide notification of such
recall to all affected Replacement
Customers no later than 9:00 a.m. on the
day Timely Nominations are due (Central
Clock time).
(B) Early Evening Recall Notification:
(1) A Releasing Customer recalling capacity
must provide notice of such recall to MRT
and the first Replacement Customer no
later than 3:00 p.m. on the day that
Evening Nominations are due;
(2) MRT will provide notification of such
recall to all affected Replacement
Customers no later than 4:00 p.m. on the
day that Evening Nominations are due
(Central Clock Time).