Centerpoint Energy - Mississippi River
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 04/01/2003, Docket: RP00-410-005, Status: Effective
Original Sheet No. 164A Original Sheet No. 164A : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
14. CAPACITY RELEASE (Continued)
of its Primary Path or to release a Secondary Path must specify
the receipt and delivery points for the segment being released.
Releasing Customer may request Primary Receipt and/or Delivery
Points for the Primary Path Segment being released within the
Primary Path up to its entitlement on that segment and for the
unreleased Primary Path Segment within the Primary Path up to its
entitlement on that segment. Releasing Customer may also request
Primary Receipt and/or Delivery Points outside its Primary Path,
subject to the entitlements and terms set forth in Section 35 of
these General Terms and Conditions. In cases where new primary
points are requested, the capacity release schedule set forth in
Section 14.4 below shall not apply, but the requests will be
processed as soon as practicable, which in most cases should be no
longer than two (2) business days after receipt, and the release
shall then be processed in accordance with Section 14.4 (b) or
(c), as applicable. The establishment of any such primary points
shall be subject to the terms of this tariff and the availability
of capacity.
(iii) The term of the release, which term must be for at
least one day (commencing at any of the effective times for
standard nomination cycles specified in Section 8.1(f)(i) above).