Midwestern Gas Transmission Company
SECOND REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/01/2000, Docket: RP00-233-000, Status: Effective
First Revised Sheet No. 18 First Revised Sheet No. 18 : Superseded
Superseding: Original Sheet No. 18
RATE SCHEDULE FT-GS (continued)
2.5 Transporter shall not be required to install, operate or maintain any
additional facilities in order to provide new transportation service under
this Rate Schedule.
3. QUALIFICATIONS FOR SERVICE
3.1 All Shippers requesting firm transportation service under this Rate Schedule
must qualify pursuant to Article XXV of the General Terms and Conditions of
Transporter's FERC Gas Tariff.
3.2 All Shippers requesting firm transportation service hereunder must execute
a Firm Gas Transportation Service Agreement for use pursuant to Rate Schedule
FT-GS (FT-GS Agreement) in accord with the provisions of Article XXV of the
General Terms and Conditions of Transporter's FERC Gas Tariff.
4. DELIVERIES AND RECEIPTS
4.1 Receipt Points: Subject to the availability of capacity, any receipt point
on Transporter's system covered by a Balancing Agreement (Eligible Receipt
Point) shall be eligible to be designated as a Primary Receipt Point(s) in
Shipper's FT-GS Agreement. Receipt points not covered by a Balancing
Agreement may be Eligible Receipt Points upon Transporter's consent. Any
Eligible receipt Point may be used as a Secondary Receipt Point; provided,
that (i) Shipper's total receipts on any day shall not exceed the
Transportation Quantity specified in its FT-GS Agreement and (ii) service for
a Shipper at a Secondary Receipt Point shall not cause a reduction of
scheduled receipts for another firm shipper utilizing a Primary or Secondary
Receipt Point. If the capacity at such Receipt Point is insufficient to
serve all Shippers requesting the point, receipt quantities for that point
shall be allocated in accordance with Section 5 of Article III of the General
Terms and Conditions. Transporter shall not be required under any
circumstances to receive gas at any Receipt Point where the total quantity
of gas scheduled for receipt on any day is less than that required for the
accurate measurement of quantities to be received.
4.2 Delivery Points: Shipper's delivery points shall be the interconnection(s)
of Transporter's system and Shipper's system, or the delivery point(s)
specified in Shipper's former SR-1 or SR-T Agreement.