Midwestern Gas Transmission Company

Third Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 06/12/2005, Docket: RP05-341-000, Status: Effective

Fourth Revised Sheet No. 262.01 Fourth Revised Sheet No. 262.01 : Effective

Superseding: Third Revised Sheet No. 262.01

 

GENERAL TERMS AND CONDITIONS

 

 

21. CAPACITY RELEASE (Continued)

 

21.12 Standard Recall and Reput Notification Periods (Continued)

 

(c) Evening Recall Notification

 

(i) A Releasing Shipper recalling capacity shall provide notice of such

recall to Company and the first Replacement Shipper no later than

5:00 p.m. (CCT).

 

(ii) Company shall provide notification of such recall to all affected

Replacement Shippers no later than 6:00 p.m. (CCT).

 

(d) Intra-day 1 Recall Notification

 

(i) A Releasing Shipper recalling capacity shall provide notice of such

recall to Company and the first Replacement Shipper no later than

7:00 a.m. (CCT).

 

(ii) Company shall provide notification of such recall to all affected

Replacement Shippers no later than 8:00 a.m. (CCT).

 

(e) Intra-day 2 Recall Notification

 

(i) A Releasing Shipper recalling capacity shall provide notice of such

recall to Company and the first Replacement Shipper no later than

2:30 p.m. (CCT).

 

(ii) Company shall provide notification of such recall to all affected

Replacement Shippers no later than 3:30 p.m. (CCT).

 

(f) Deadline for Reput

 

The deadline for notifying Company of a reput is 8:00 a.m. (CCT) to allow

for timely nominations to flow on to the next Gas Day. [5.3.54/v1.7]

 

For recall notifications provided to Company prior to the recall notification

deadlines above (NAESB WGQ Standard 5.3.44) and received between 7:00 a.m. and

5:00 p.m. (CCT), Company shall provide notification to all affected Replacement

Shippers no later than one hour after receipt of such recall notification.

[5.3.45/v1.7]

 

For recall notification provided to Company after 5:00 p.m. and prior to

7:00 a.m. (CCT), Company shall provide notification to all affected Replacement

Shippers no later than 8:00 a.m. (CCT) after receipt of such recall

notification. [5.3.45/v1.7]

 

The Releasing Shipper shall provide capacity recall notification to its

affected Replacement Shipper(s) at the same time it provides notification to

Company. The mode of notification shall be mutually agreed between the

Releasing Shipper and its Replacement Shipper(s). [5.1.2/v1.7]

 

In the event of an intra-day capacity recall, Company shall determine the

allocation of capacity between the Releasing Shipper and the Replacement

Shipper(s) based upon the Elapsed Prorata Capacity (EPC). Variations to the

use of EPC may be necessary to reflect the nature of Company's tariff,

services, and/or operational characteristics. [5.3.56/v1.7]