Midwestern Gas Transmission Company
Third Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 01/07/2008, Docket: RP08- 49-000, Status: Effective
Third Revised Sheet No. 50 Third Revised Sheet No. 50 : Pending
Superseding: Second Revised Sheet No. 50
RATE SCHEDULE FT-A
FIRM TRANSPORTATION SERVICE
1. AVAILABILITY
This Rate Schedule is available for the transportation of natural gas on the Mainline
on a firm basis by Company for any Shipper.
Mainline shall be defined as the 30-inch diameter pipeline and appurtenant facilities
extending from an interconnection between Company and Tennessee Gas Pipeline Company
near Portland, Tennessee and extending to a point of interconnection between Company
and ANR Pipeline Company located near Joliet, Illinois.
2. APPLICABILITY AND CHARACTER OF SERVICE
2.1 The service contracted shall be the receipt of natural gas and the delivery of
the Equivalent Quantity of natural gas up to the Transportation Quantity for
the Transportation Path set forth in Exhibit A of the FT-A Agreement performed
under Part 284 of the Commission's Regulations. This service shall be provided
to the extent Company determines firm capacity is available on the Mainline to
any Shipper in the order in which each Shipper has fulfilled the requirements
of Section 3 below.
2.2 Service shall be allocated and scheduled pursuant to Subsections 3.7, 3.8 and
Section 15 of the General Terms and Conditions of Company's FERC Gas Tariff.
However, service may be curtailed for any of the reasons set out in Section 10
of the General Terms and Conditions of Company's FERC Gas Tariff or whenever
necessary to maintain gas quality or the integrity of Company's system.
2.3 Company shall not be required to install, operate or maintain any additional
facilities in order to provide new transportation service under this Rate
Schedule.
3. REQUEST FOR SERVICE
3.1 All Shippers requesting firm transportation service under this Rate Schedule
must qualify pursuant to Section 25 of the General Terms and Conditions of
Company's FERC Gas Tariff.
3.2 All Shippers requesting firm transportation service hereunder must execute a
Firm Gas Transportation Agreement for use under Rate Schedule FT-A
(FT-A Agreement) in accordance with the provisions of Section 25 of the General
Terms and Conditions of Company's FERC Gas Tariff.
4. DELIVERIES AND RECEIPTS
4.1 Receipt Points
Subject to the availability of capacity, any Receipt Point on Company's
Mainline shall be eligible for designation as a Primary Receipt Point
for gas transported under this Rate Schedule pursuant to
Subsection 15.2 of the General Terms and Conditions of Company's FERC
Gas Tariff.