American Midstream (Midla), LLC

Sixth Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 05/01/2010, Docket: RP10-483-000, Status: Effective

Original Sheet No. 143 Original Sheet No. 143

 

9.8 If presentation of a bill by Pipeline is delayed after the 9th business day of the

month, then the time of payment shall be extended accordingly unless Customer is

responsible for such delay.

 

10. CONSTRUCTION OF NEW FACILITIES AND ASSOCIATED FEES

 

10.1 Pipeline shall have no obligation to construct facilities to receive, redeliver,

transport, or exchange Natural Gas; provided, however, if Customer requests and

Pipeline, on a non-discriminatory basis, elects to construct such facilities, Customer shall,

at Pipeline's request, reimburse Pipeline for all costs incurred for facilities Pipeline

constructs to receive, redeliver, transport or exchange, Gas volumes for Customer.

 

10.2 Customer shall reimburse Pipeline for any filing or other fees which Pipeline is

obligated to pay to the FERC or any other governmental authorities to implement or

continue any service provided pursuant to this FERC Gas Tariff. Any reimbursement

due Pipeline by Customer pursuant to this Section 10 shall be due and payable to

Pipeline within ten (10) Days of receipt by Customer of Pipeline's invoice for such

reimbursement.

 

10.3 In the event Pipeline elects to construct facilities pursuant to this Section 10, any

Gas which is lost as a result of such construction shall be replaced by Customer at a time

and place and in such quantities as determined by Pipeline; provided, however,

Customer shall not be responsible for replacing those quantities lost due to the negligence

of Pipeline.

 

11. LATERAL LINE POLICY

 

11.1 To the extent that Pipeline elects to provide service pursuant to this FERC Gas

Tariff, it shall be Pipeline's policy to finance, construct, own, and operate laterals serving

Customers. This policy shall be applicable to the financing, construction, ownership, and

operation of laterals serving both existing and prospective Customers under Pipeline's

Rate Schedules contained in this FERC Gas Tariff.