American Midstream (Midla), LLC
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/01/2010, Docket: RP10-483-000, Status: Effective
Original Sheet No. 110 Original Sheet No. 110
4. CAPACITY RELEASE
4.1 (a) This section sets forth a capacity release program under which a Releasing
Customer can release all or part of its firm capacity back to Pipeline for assignment to a
Potential Customer or a Prearranged Customer that is seeking the capacity of the
Releasing Customer by entering into a Service Agreement with Pipeline. Pipeline will
permit segmentation of capacity right held by Customer(s) including Replacement
Customer(s), to the maximum extent it is operationally feasible. Provided, however, that
a Releasing Customer shall not be permitted to release capacity until the Potential
Customer or a Prearranged Customer enters into a Service Agreement with Pipeline for
such released capacity. Provided, further, that the above requirement for contracting
shall not inhibit the ability of the Replacement Customer to submit a nomination at the
next available opportunity after the Pipeline is notified of the release.
until
(b) A Releasing Customer may release capacity held pursuant to 18 C.F.R. Subparts B
or G of Part 284 of the Commissions' regulations. A Releasing Customer which receives
service under a firm Rate Schedule under this FERC Gas Tariff is permitted to release its
capacity in whole or in part, including any segments of its capacity, and on a permanent
or temporary basis. When a Releasing Customers assigns its service rights by segments
and/or assigns only a portion of its MDQ under that agreement, the Releasing Customer's
Service Agreement shall be deemed to be modified in accordance with the assignment
and the Releasing Customer will be able to utilize only the unassigned service rights
during the term of the release.