American Midstream (Midla), LLC
Sixth Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 05/01/2010, Docket: RP10-483-000, Status: Effective
Original Sheet No. 49 Original Sheet No. 49
(c) The date on which Customer is notified that any facilities necessary to provide the
requested service are ready for service; or
(d) The date on which any necessary governmental approvals or authorizations are
received and accepted by the appropriate party.
3.4 Customer's Service Agreement shall be terminated if, after commencement of initial
service, Customer fails to nominate or tender Gas within thirty (30) Days after notice by
Pipeline of its intent to terminate Customer's Service Agreement by reason of failure of
Customer to transport Gas for a six (6) Month consecutive period.
3.5 Customer's failure to schedule transportation shall be excused by an event of force
majeure, as defined in Section 13 of the General Terms and Conditions; provided,
however, such failure to schedule transportation shall be excused only for the duration of
the force majeure event.
4. RATE
4.1 The rate for interruptible transportation service provided under this Rate Schedule
shall be the amount negotiated by Pipeline and Customer, which shall not be more than
the maximum, nor less than the minimum for this Rate Schedule as set forth on currently
effective Tariff Sheet No. 4A.
4.2 (a) For all services that utilize a Receipt or Delivery Point on Pipeline's
mainline system (other than services from Receipt/Delivery Points on the T-32 lateral or
other offsystem laterals), Pipeline shall have the right to retain one and one-half percent
(1.5%) of the quantities of Gas delivered to Pipeline for Fuel Reimbursement. Any
change in such fuel rate shall be made effective only at the beginning of a Month.
(b) For those services involving T-32 Receipt/Delivery Points, Pipeline shall have the
right to retain, from the quantities of Gas delivered to Pipeline, a Fuel Reimbursement
percentage applicable to service on the T-32 lateral ("T-32 Fuel Reimbursement") equal
to the actual fuel and unaccounted for on the T-32 lateral. Until changed in a filing
accepted by the FERC, the T-32 Fuel Reimbursement percentage will be zero. Any
change in such fuel rate shall be made effective only at the beginning of a Month.
(c) For those services involving Receipt and Delivery Points located entirely on
laterals not contiguous to Pipeline's mainline system, Pipeline shall not retain any Gas as
Fuel Reimbursement.