American Midstream (Midla), LLC

Sixth Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 05/01/2010, Docket: RP10-483-000, Status: Effective

Original Sheet No. 21 Original Sheet No. 21

 

1.4 Unless otherwise agreed to by Pipeline and subject to Section 10 of the General

Terms and Conditions of this FERC Gas Tariff, service under this Rate Schedule shall

not be available to the extent that Pipeline would be required to construct, modify, expand

or acquire any facilities to enable Pipeline to perform the requested services; provided,

however, if Customer requests and Pipeline, on a non-discriminatory basis, elects to

construct such facilities, Customer shall, at Pipeline's request, reimburse Pipeline for all

costs and associated fees, licenses and other expenses incurred by Pipeline for the

construction, modification, expansion or acquisition of facilities to enable Pipeline to

perform the requested services.

 

1.5 Availability of service hereunder shall be subject to compliance by the party

requesting service with all other provisions of this Rate Schedule NNS and the General

Terms and Conditions of this FERC Gas Tariff.

 

 

 

2. APPLICABILITY AND CHARACTER OF SERVICE

 

2.1 (a) Service hereunder shall entitle Customer to receive quantities in excess of its

nomination(s) under a firm transportation Rate Schedule up to Customer's no-notice

MDQ. This service shall consist of the