29. DEFERRED TRANSPORTATION COST ADJUSTMENT PROVISION
(a) Purpose. This Section establishes the mechanism ("Deferred
Transportation Cost Adjustment") for the passthrough by
Transporter of the over/underrecovery of costs related to
FERC Account No. 858 capacity that Transporter is authorized
pursuant to Commission orders to maintain or replace, as
defined in Section 29(a)(1), below, ("Qualifying
Transportation Costs"). The base rates and charges
applicable to all Rate Schedules shall be adjusted, where
applicable, by Transporter on an annual basis to reflect an
adjustment of Qualifying Transportation Costs