ANR Pipeline Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2003, Docket: RP00-332-007, Status: Effective
Sub Fifth Revised Sheet No. 154 Sub Fifth Revised Sheet No. 154 : Effective
Superseding: Sub Fourth Revised Sheet No. 154
GENERAL TERMS AND CONDITIONS
(Continued)
(3) Any release under Rate Schedule NNS shall be subject to all of the limitations
of Rate Schedule NNS and shall only be releasable at the Primary Delivery
Point(s) specified in the underlying Rate Schedule NNS Agreement.
(4) Any release under Rate Schedule FTS-2 shall be subject to the same
interruption(s) of service thereunder as set forth in such Rate Schedule
FTS-2.
(5) Any Replacement Shipper that acquires capacity pursuant to a segmented release
shall acquire Secondary Receipt and Delivery Points unless the Releasing Shipper
has agreed to release all or part of the capacity at the Primary Receipt and/or
Delivery Points. With the prior consent of the Releasing Shipper, as expressed
in the capacity release notice, a Replacement Shipper that acquires Primary
Receipt and/or Delivery Points may request a change in such point(s) from
Transporter pursuant to Section 2.4 of these General Terms and Conditions. In
addition, a Replacement Shipper that acquires Secondary Receipt and/or Delivery
Points shall have the right to request that Transporter elevate such point(s) to
Primary Points subject to the conditions set forth below and in accordance with
Sections 2.4 and 10.3, as applicable, of these General Terms and Conditions. In
addition, the following provisions will apply.
(i) For any contractual path traversing the Northern Segment, only Secondary
Points included in the released segment within the Primary Route of the
Releasing Shipper's Agreement shall be eligible for elevation by the
Replacement Shipper as Primary Points.
(ii) No point may be elevated to a Primary Point if such point is not eligible
for treatment as a Primary Point under these General Terms and Conditions
and Shipper's Rate Schedule.
(iii) For any contractual path traversing the Northern Segment, a request
to elevate a Secondary Point to a Primary Point may not change the
contractual direction of flow of the original Releasing Shipper's
Agreement.