GENERAL TERMS AND CONDITIONS
(Continued)
(1) During the Winter Period, to the extent a Shipper
under Rate Schedules ETS, FTS-1, FTS-2, FTS-4, FTS-
4L, FSS, OR FTS-3 releases capacity, its NNE, if
any, at Primary Delivery Point(s) will not be
diminished; provided, however, that if the MDQ under
such Rate Schedules is released below the Shipper's
NNE at any Delivery Point, then the otherwise
applicable NNE at such Delivery Point shall be
reduced to the level of the remaining MDQ at such
Delivery Point.
(2) Any release under Rate Schedule FSS shall be subject
to the limitation that, under any affected Agreement,
the ratio of the Maximum Storage Quantity to the Base
Maximum Daily Withdrawal Quantity shall remain
constant for both the Releasing Shipper's and
Replacement Shipper's Agreements. Nothing contained
herein is intended to restrict a Shipper from
releasing its Rate Schedule FSS capacity separate
from any associated transportation entitlement.