ANR Pipeline Company

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/01/2006, Docket: RP06-613-000, Status: Effective

Third Revised Sheet No. 135 Third Revised Sheet No. 135 : Effective

Superseding: Second Revised Sheet No. 135

GENERAL TERMS AND CONDITIONS

(Continued)

 

(a) If the actual flow through the meter represents a delivery

by Transporter, then the nominated receipts shall be

allocated as nominated and the sum of such receipts shall be

added to the metered quantity before any allocation is made

in accordance with Section 14.1, above; or

 

(b) If the actual flow through the meter represents a receipt by

Transporter, then the nominated deliveries shall be

allocated as nominated (as adjusted by the BTAs for the Rate

Schedule MBS Shippers) and the sum of such deliveries shall

be added to the metered quantity before any allocation is

made in accordance with Section 14.2, above.

 

14.4 Prior Period Adjustments.

 

(a) In accordance with the provisions of Sections 12.3, 12.4,

17.1 and 17.3 of these General Terms and Conditions,

Transporter shall use the best information available to

close its allocation of quantities for a Service Month five

(5) business days after such Service Month. To the extent

that adjustments are made after the date of such close such

adjustments ("Prior Period Adjustments" or "PPA") shall be

treated under this Section 14.4. If the PPA are due to the

correction of measurement data or allocations, such

adjustments should be processed within six (6) Months of the

applicable Service Month. If the affected party disputes

the as-adjusted quantity, it is entitled to rebut the basis

for the PPA, but only if it does so within three (3) Months

of the processing of the as-adjusted quantity.

Notwithstanding the above-specified deadlines for

processing/rebutting PPAs, such deadlines shall not apply in

the case of deliberate omission or misrepresentation or

mutual mistake of fact. Parties' other statutory or

contractual rights shall not be diminished by this standard.

 

(b) If an adjustment is required at a Receipt Point, such

adjustment shall be allocated to the operator of facilities

immediately upstream of that Receipt Point or the producer.

If the adjustment results in an increase in the measured

quantity, Transporter shall pay such operator or the

producer an amount (as full consideration, inclusive of

taxes and any other