ANR Pipeline Company

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 03/01/2007, Docket: RP04-435-006, Status: Effective

Original Sheet No. 131.03 Original Sheet No. 131.03 : Effective

 

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

(vii) Where the Transporter can not fully correct an HDP

Problem by posting a Hydrocarbon Dewpoint limit in

the most downstream HDP Segment experiencing or

anticipating to experience a HDP Problem, it may post

a Hydrocarbon Dewpoint limit in subsequent upstream

HDP Segment(s) but the Hydrocarbon Dewpoint limit in

the subsequent HDP Segment(s) may be no stricter than

the limit in the first HDP Segment. Where the

Hydrocarbon Dewpoint of an upstream Monitoring Point

complies with the posted Hydrocarbon Dewpoint limit,

Transporter shall not apply any Hydrocarbon Dewpoint

limit to that point or any other upstream receipt

point in the sequential HDP Segment.

 

(viii) When Transporter posts a Hydrocarbon Dewpoint limit

on the Sandwich - Georgetown - Defiance HDP Segment

(the SGD HDP Segment) then the gas receipts into the

SGD HDP Segment either from interconnects or from any

adjacent HDP Segment feeding gas directly into the

SGD HDP Segment must meet the posted HDP limit for

the SGD HDP Segment.

 

(ix) Transporter will not require processing of gas at

receipt points upstream of the tailgate of a straddle

plant that meets the posted Hydrocarbon Dewpoint

limit without processing.

 

(x) To the extent operationally practicable, Transporter

may allow gas that does not meet a posted Hydrocarbon

Dewpoint limitation at receipt points to continue to

flow provided that Transporter approves a "pairing"

proposal as set forth in Section 13.3(c).

 

(xi) Transporter shall allow gas that does not meet a

posted Hydrocarbon Dewpoint limitation at receipt

points to continue to flow provided that the Shipper

or a third party provides to Transporter proof of

processing at a plant within the HDP Segment where

the gas at the tailgate of that plant satisfies the

Hydrocarbon Dewpoint limitation for the applicable

HDP Segment.