ANR Pipeline Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 11/02/1998, Docket: RP99- 61-000, Status: Effective
Second Revised Sheet No. 110A Second Revised Sheet No. 110A : Effective
Superseding: First Revised Sheet No. 110A
GENERAL TERMS AND CONDITIONS
(Continued)
(b) Subject to upstream and downstream operators' confirmations and
Transporter's operating conditions, an intra-day nomination
submitted pursuant to one of the deadlines set forth in Section
6.1(a), above, can be used to request increases or decreases in
total flow, changes to Receipt Points, or changes to Delivery
Points, of scheduled Gas. Transporter will not accept a reduced
intra-day nomination for any quantity deemed already delivered
based on an elapsed-prorated-scheduled quantity.