RATE SCHEDULE NNS

No-Notice Service

(Continued)

 

its nominations at such Delivery Point under the NNS Supply

Transportation Agreement, so long as such quantity does not

exceed the NNE specified for such Delivery Point. This

service shall be firm up to the Delivery Point NNE; provided,

however, if the NNS Storage Transportation is an Agreement

under Rate Schedule ETS, service hereunder shall be firm up to

the aggregate NNE, after netting at all Delivery Points.

 

(b) The difference between the sum of nominations and the allocated

quantities at a Delivery Point for the NNS Supply Transportation

shall be deemed a no-notice quantity and allocated as an

injection to or withdrawal from the Designated Storage Account

and transported under the NNS Storage Transportation, as

applicable.

 

(c) Service under the NNS Storage Transportation and Firm Storage

Service Agreements can exceed the applicable Delivery Point MDQ

or storage MDIQ and MDWQ by the NNE associated with such

Delivery Point, except during withdrawals during the Winter

Period.

 

(d) Notwithstanding the foregoing provisions of this Section 2, if

Shipper fails to meet its good faith obligations under Section 4

of this Rate Schedule, then Transporter's obligations under this

Rate Schedule shall be best efforts only.

 

3. CHARGES

 

Each Month Shipper shall pay to Transporter the following charges:

 

3.1 Reservation Charge.

 

(a) The Reservation Rate shown on Sheet No. 11 for each

Dekatherm of NNE of Shipper under this Rate Schedule;

 

(b) If, on any Day, Transporter fails to Tender the lawful

quantity of Gas that Shipper would otherwise have taken

at the Delivery Point(s), due to the Transporter's

scheduling of necessary maintenance and repair of

pipeline facilities, necessary maintenance and repair of

compression facilities, and/or facility outages for tie-

in of new facilities, then the portion of the Monthly

bill of such Shipper which is attributable to the

Reservation