ANR Pipeline Company

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 11/01/2006, Docket: RP06-613-000, Status: Effective

Second Revised Sheet No. 45I Second Revised Sheet No. 45I : Effective

Superseding: First Revised Sheet No. 45I

 

 

RATE SCHEDULE ITS-3

Interruptible Transportation Service

 

 

1. AVAILABILITY

 

This Rate Schedule is available to any person, corporation,

partnership or any other party (hereinafter referred to as "Shipper")

for the Transportation of Gas by Transporter, provided that the

applicable end user agrees to allow Transporter, in cooperation with

any intervening downstream transporter, to install telemetered

electronic measurement, and other necessary facilities, as reasonably

required in order to provide service.

 

2. APPLICABILITY AND CHARACTER OF SERVICE

 

(a) This Rate Schedule shall apply to all Transportation Service

rendered by Transporter for Shipper pursuant to the executed

Agreement under this Rate Schedule.

 

(b) Transportation Service under this Rate Schedule shall consist

of: (1) the receipt of Gas on behalf of Shipper, (2) the

Transportation of Gas, and (3) the Tender of Gas for delivery

by Transporter to Shipper, or for Shipper's account.

 

(c) Transportation Service rendered under this Rate Schedule shall

be interruptible. Interruptible service shall be available

only to the extent of actual available capacity as it may exist

from time to time under current conditions, and shall be

offered in accordance with the priorities established in the

General Terms and Conditions of this Tariff. The Dekatherms

delivered in one Hour may be requested by Shipper to be

provided on a best efforts basis, but shall be no less than

1/24th and no greater than 1/4th of the total Dekatherms

nominated and scheduled for delivery during the same Day.

 

3. CHARGES

 

Each Month Shipper shall pay to Transporter the following charges:

 

3.1 Commodity Charges.