ANR Pipeline Company

Second Revised Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 04/01/2009, Docket: RP09-428-000, Status: Suspended

First Revised Sheet No. 10A First Revised Sheet No. 10A

Superseding: Original Sheet No. 10A

 

RATE SCHEDULE FSS

RESERVATION AND COMMODITY CHARGES

FIRM STORAGE SERVICE 1/

 

APPLICABLE TO CUSTOMERS UTILIZING CAPACITY PURSUANT TO INCREMENTAL FACILITY EXPANSIONS:

 

Docket No. CP06-464 (Cold Springs 1 Storage Project):

-----------------------------------------------------

Maximum

Maximum Minimum Daily Capacity

Rate per Dth Rate per Dth Release Rate per Dth

------------ ------------- --------------------

With Ratchets and Seasonal Entitlements

---------------------------------------

1. Reservation Rate

a. Deliverability Rate $ 2.28 $ 0 $ 0.0750

b. Capacity Rate $ .4818 $ 0 $ 0.0013

2. Commodity Rate

Injection/Withdrawal $ 0.0126 $ 0.0126

3. Overrun Service Rate 2/ $ 0.0126

4. Transporter's Use (%) and EPC Charge 3/

 

With Ratchets and Flexible Entitlements

---------------------------------------

1. Reservation Rate

a. Deliverability Rate $ 2.68 $ 0 $ 0.0881

b. Capacity Rate $ .4818 $ 0 $ 0.0013

2. Commodity Rate

Injection/Withdrawal $ 0.0126 $ 0.0126

3. Overrun Service Rate 2/ $ 0.0126

4. Transporter's Use (%) and EPC Charge 3/

 

Without Ratchets and Seasonal Entitlements

------------------------------------------

1. Reservation Rate

a. Deliverability Rate $ 2.85 $ 0 $ 0.0937

b. Capacity Rate $ .4818 $ 0 $ 0.0013

2. Commodity Rate

Injection/Withdrawal $ 0.0126 $ 0.0126

3. Overrun Service Rate 2/ $ 0.0126

4 Transporter's Use (%) and EPC Charge 3/

 

Without Ratchets and Flexible Entitlements

------------------------------------------

1. Reservation Rate

a. Deliverability Rate $ 3.25 $ 0 $ 0.1068

b. Capacity Rate $ .4818 $ 0 $ 0.0013

2. Commodity Rate

Injection/Withdrawal $ 0.0126 $ 0.0126

3. Overrun Service Rate 2/ $ 0.0126

4. Transporter's Use (%) and EPC Charge 3/

 

RATE SCHEDULE DDS 1/

---------------------

1. Storage Commodity Rate $ .0993 $ 0.0126

 

1/ The rates shown are subject to all applicable reservation and volumetric charges or

surcharges under Section 24 of the General Terms and Conditions of this Tariff. Sheet

No. 17 reflects the applicable charges and surcharges under this Section.

2/ 100% load factor rate, which is the sum of (a) the product of (1) the Deliverability

Reservation Rate, (2) twelve, and (3) the Base Maximum Daily Withdrawal Quantity divided

by the Maximum Storage Quantity, (b) the Capacity Reservation Rate and (c) the

Injection/Withdrawal Commodity Rate.

3/ For Rate Schedule FSS and DDS, Transporter's Use (%): 2.06%

For Rate Schedule FSS and DDS, EPC Charge: $0.1060

Transporter's Use (%) and EPC Charge on storage Gas transfers is subject to Section 18.12

of the General Terms and Conditions of this Tariff.