9. CERTIFICATION

 

At the time Shipper executes a Service Agreement, unless the Gas

to be transported is for the system supply of a local distribution

company, interstate pipeline, or intrastate pipeline, Shipper

shall identify to MGS all corporate entities ultimately receiving

the gas to be transported, and shall provide verification that

these entities have signed contracts to purchase such gas. Within

seven (7) days after transportation service begins, Shipper shall

identify to MGS all other transporting entities, including

interstate pipelines, that will provide transportation incidental

to the service provided by MGS.