Millennium Pipeline Company, L. L. C.

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index

 

 

Effective Date: 12/22/2008, Docket: CP98-150-011, Status: Effective

Original Sheet No. 294 Original Sheet No. 294

 

GENERAL TERMS AND CONDITIONS

(Continued)

 

(b) The annual amount of the facility charge shall be established

starting with the first day of the calendar month in which Transporter shall

have completed or made available for operation the facilities requested by

Shipper. Such amount shall be estimated by Transporter when the facilities

are made available and at the beginning of each calendar year thereafter,

unless otherwise agreed. Each month, Transporter will bill Shipper for one-

twelfth of the estimated annual facility charge. An adjustment will be made

if necessary at the end of each calendar year to reflect the cost applicable

to said facilities for the year.

 

27.3 Agreement. In each case where Transporter agrees to construct

facilities at the request of the Shipper, unless otherwise agreed, the

Service Agreement will contain as an Exhibit thereto an agreement concerning

such facilities, executed in the form as set forth in this Tariff.