RATE SCHEDULE SH-1

Kern River Firm Transportation Services

(Continued)

 

ARTICLE 5 - CAPACITY RELEASE PROGRAM (Continued)

 

5.8 Applicable Deadlines. (Continued)

 

For biddable releases (less than 1 year):

 

(1) offers should be tendered by 12:00 p.m. on a Business

Day;

 

(2) open season ends no later than 1:00 p.m. on a Business

Day (evaluation period begins at 1:00 p.m. during

which contingency is eliminated, determination of best

bid is made, and ties are broken);

 

(3) evaluation period ends and award posting if no match

required at 2:00 p.m.;

 

(4) match or award is communicated by 2:00 p.m.;

 

(5) match response by 2:30 p.m.;

 

(6) where match required, award posting by 3:00 p.m.;

 

(7) contract issued within one hour of award posting (with

a new contract number, when applicable); nomination

possible beginning at the next available nomination

cycle for the effective date of the contact. (Central

Clock Time)

 

For biddable releases (1 year or more):

 

(1) Offers should be tendered by 12:00 p.m. four Business

Days before award;

 

(2) open season ends no later than 1:00 p.m. on the

Business Day before timely nominations are due (open

season is three Business Days);

 

(3) evaluation period begins at 1:00 p.m. during which

contingency is eliminated, determination of best bid

is made, and ties are broken;

 

(4) evaluation period ends and award posting if no match

required at 2:00 p.m.;

 

(5) match or award is communicated by 2:00 p.m.;