Kern River Gas Transmission Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/01/2000, Docket: RP00-288-000, Status: Effective
Original Sheet No. 827 Original Sheet No. 827 : Superseded
RATE SCHEDULE SH-1
Kern River Firm Transportation Services
(Continued)
ARTICLE 5 - CAPACITY RELEASE PROGRAM (Continued)
5.5 Bidding for Transportation Rights. (Continued)
pursuant to this Section 5.5(d) may, at any time during the
Bidding Period, submit one or more subsequent bids in accordance
with this Section 5.5 for the same Release Request; provided,
however, that Bidder may not submit a subsequent bid without first
withdrawing an existing bid, and provided further that any
subsequent bid submitted must contain a higher Total Release
Reservation Charge than contained in any previous bid which Bidder
has submitted for the same Release Request.
5.6 Determination of Successful Bidder.
(a) GISB 5.3.3: "For the capacity release business process timing
model, only the following methodologies are required to be
supported by capacity release service providers and provided to
releasing shippers as choices from which they may select and, once
chosen, should be used in determining the awards from the bid(s)
submitted. They are: 1) highest rate, 2) net revenue and 3)
present value. Other choices of bid evaluation methodology
(including other releasing shipper defined evaluation
methodologies) can be accorded similar timeline evaluation
treatment at the discretion of the capacity release service
provider. However, the capacity release service provider is not
required to offer other choices or similar timeline treatment for
other choices, nor, is the capacity release service provider held
to the timeline should the releasing shipper elect another method
of evaluation."
The Release Request must specify one of the following three
methodologies for determining the award from the bids submitted:
1) highest rate, 2) net revenue, or 3) present value. GISB 5.3.4:
"When the capacity release service provider makes awards of
capacity for which there have been multiple bids meeting minimum
conditions, the capacity release facilitator should award the
bids, best bid first, until all offered capacity is awarded." If