Kern River Gas Transmission Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 02/03/2002, Docket: RP02-137-000, Status: Effective
First Revised Sheet No. 730 First Revised Sheet No. 730 : Effective
Superseding: Original Sheet No. 730
RATE SCHEDULE MO-1
Kern River Firm Transportation Services
(Continued)
ARTICLE VI - MEASUREMENT OF GAS (Continued)
6.1 Measuring Equipment (Continued)
(c) If neither of the methods provided in (a) nor (b) above can
be used, by estimating the quantity delivered by reference
to deliveries under similar conditions during a period when
the equipment was registering accurately. No correction
shall be made in the recorded volumes of Gas delivered
hereunder for inaccuracies in measuring equipment of one
percent (1%) or less.
6.1.5 New Measurement Techniques. If, at any time during the term of
the Transportation Service Agreement a new method or technique is
developed with respect to Gas measurement, such new method or
technique may be substituted for the Gas measurement set forth in
this Article VI upon mutual agreement thereto by the parties in
writing.
6.1.6 Correction of Stated Metered Volumes. GISB 2.3.14: "Measurement
data corrections will be processed within six (6) months of the
production month with a three (3) month rebuttal period. This
standard will not apply in the case of deliberate omission or
misrepresentation or mutual mistake of fact. Parties' other
statutory or contractual rights shall not otherwise be diminished
by this standard."
6.2 Measurement Procedures.
6.2.1 Metering. The Gas shall be metered by either orifice, turbine or
ultrasonic type meters, at the discretion of Transporter. When
orifice meters are used, they shall be installed and maintained,
and volumes shall be measured in accordance with the methods
prescribed in ANSI/API 2530, dated September 1985 or any