Kern River Gas Transmission Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/01/2000, Docket: RP00-288-000, Status: Effective
Original Sheet No. 644 Original Sheet No. 644 : Effective
RATE SCHEDULE UP-1
Kern River Firm Transportation Services
(Continued)
ARTICLE XIV - PRIORITY OF SERVICE
14.1 Curtailment. If Transporter determines on any Day that for any reason
whatsoever, including reasons of force majeure, the capacity of
Transporter's System or any portion thereof is insufficient to satisfy
the requirements for Transportation service as set forth in executed
transportation agreements, Transporter shall curtail or interrupt
receipts and deliveries.
Subject to the balancing provisions of Section 4.2 herein such
curtailment shall be limited to the portion of Transporter's System on
which capacity is reduced and shall be in accordance with the priorities
set forth in Section 13.3 of the General Terms and Conditions of this
tariff.