RATE SCHEDULE UP-1
Kern River Firm Transportation Services
(Continued)
ARTICLE IX - FORCE MAJEURE (Continued)
9.1 Force Majeure. (Continued)
9.1.2 Monthly Demand Charge Adjustment. Nothing in this Article IX
shall relieve Shipper of payment of the Monthly Demand Charge
Amount, unless and until the total number of days per occurrence
of force majeure that Transporter is unable to transport gas on
behalf of Shipper due to a condition(s) of force majeure,
exceeds thirty (30) days. Shipper shall be relieved of payment
of the Daily Reservation/Demand Rate for all days that
Transporter is unable to transport gas on behalf of Shipper due
to a condition(s) of force majeure in excess of thirty (30) days
per occurrence of force majeure; provided, however, that no
adjustment to the Monthly Demand Charge shall be made for any
interruption or curtailment of service at any Secondary Receipt
Point or Secondary Delivery Point. The provisions of this
Section 9.1.2 shall be superceded by any alternative force
majeure provisions that are made effective pursuant to
procedures agreed to by Transporter and Shipper and included in
the Transportation Service Agreement executed by Transporter and
Shipper.