Kern River Gas Transmission Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 06/01/2002, Docket: RP02-248-000, Status: Effective
Original Sheet No. 213 Original Sheet No. 213 : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
27. AVAILABLE CAPACITY (Continued)
27.5 Right of First Refusal. (Continued)
(b) If a Shipper chooses to exercise a right of first refusal
for only a portion of its capacity, or chooses to extend the
primary term of its agreement pursuant to a contractual
rollover or evergreen provision for only a portion of its
capacity, Shipper's MDQ, aggregate Maximum Receipt Volume
entitlements and aggregate Maximum Delivery Volume
entitlements all must be retained by the same percentage.
(c) If an existing Shipper chooses not to match the economic
value of the best bid(s) as determined by Transporter,
capacity will be awarded to the selected bidder(s), and the
existing Shipper's right of first refusal will expire.
(d) If no creditworthy bids are submitted for any portion of the
capacity, an existing Shipper will be entitled to continue
its existing service for any portion of the capacity, for
any term desired, provided Transporter and Shipper agree to
mutually acceptable rates for the service at a level within
the posted maximum and minimum tariff rates for the
applicable service or at a mutually acceptable Negotiated
Rate for the applicable service. If Transporter and Shipper
fail to agree on rates within thirty (30) days of the bid
close date, Shipper's right of first refusal will be deemed
to have terminated.
27.6 Notwithstanding anything to the contrary set forth in this
Section 27, Transporter will not be required to provide service at
any rate less than the maximum rate for Rate Schedule KRF-1, as
such rate may vary from time to time.