Kern River Gas Transmission Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/01/2003, Docket: RP03-374-000, Status: Effective
Third Revised Sheet No. 155 Third Revised Sheet No. 155 : Effective
Superseding: 1st Rev First Revised Sheet No. 155
GENERAL TERMS AND CONDITIONS
(Continued)
15. CAPACITY RELEASE PROGRAM (Continued)
15.8 Applicable Deadlines. (Continued)
For biddable releases (1 year or more):
(1) Offers should be tendered by 12:00 p.m. four Business Days
before award;
(2) open season ends no later than 1:00 p.m. on the Business Day
before timely nominations are due (open season is three
Business Days);
(3) evaluation period begins at 1:00 p.m. during which
contingency is eliminated, determination of best bid is
made, and ties are broken;
(4) evaluation period ends and award posting if no match
required at 2:00 p.m.;
(5) match or award is communicated by 2:00 p.m.;
(6) match response by 2:30 p.m.;
(7) where match required, award posting by 3:00 p.m.;
(8) contract issued within one hour of award posting (with a new
contract number, when applicable); nomination possible
beginning at the next available nomination cycle for the
effective date of the contract. (Central Clock Time)
For non-biddable releases:
(1) Timely Cycle
(i) posting of prearranged deals not subject to bid are
due by 10:30 a.m.;
(ii) contract issued within one hour of award posting (with
a new contract number, when applicable); nomination
possible beginning at the next available nomination
cycle for the effective date of the contract. (Central
Clock Time)