13. SCHEDULING OF RECEIPTS AND DELIVERIES (Continued)
13.5 Allocation of Deliveries.
Unless prohibited by applicable law or regulation, the quantities
delivered by Transporter at any Delivery Point will be allocated
among Shippers and services as follows:
(a) In accordance with any allocation procedures specifically
agreed to by Transporter and the Interconnect Operator of
Delivery Point(s) as set forth in the Operational Balancing
Agreement; provided, however, Transporter will not be
required to enter into agreements with such Interconnect
Operators if they are not creditworthy in accordance with
the provisions set forth in Section 29 of the General Terms
and Conditions of this tariff.
(b) In the absence of a methodology set forth in 13.5(a) above,
Shipper will cause the Interconnect Operator at the Delivery
Point to notify Transporter of the pre-determined allocation
("PDA") methodology to be utilized in determining actual
deliveries among all Shippers and services scheduling
service at such Delivery Point. Such notification may be
submitted electronically to Transporter's Designated Site
or, if mutually agreed between Transporter and Shipper, by
other modes of communication. NAESB WGQ 2.3.5: "The upstream
or downstream party providing the point confirmation should
submit the PDA to the allocating party after or during
confirmation and before the start of the gas day." Such PDA
will be effective for the term specified in the PDA
agreement provided that such term may not cover a period of
less than one Day. The chosen methodology must allocate
deliveries, to the maximum extent possible, based upon
confirmed nominations.
(c) In the absence of a methodology as described in 13.5(a) or
(b) above, Transporter may rely on its default methodology
of allocating quantities to all Shippers. NAESB WGQ 2.3.18:
"The types of allocation methodologies is a list from which
two parties may agree. If the two parties cannot agree upon
an allocation methodology, pro rata based upon confirmed
nominations should be used as the default method. The party
responsible for custody transfer (the party performing the
measurement function) should provide the allocation."