Kern River Gas Transmission Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/2009, Docket: RP09-723-000, Status: Effective
Third Revised Sheet No. 124 Third Revised Sheet No. 124
Superseding: Second Revised Sheet No. 124
. GENERAL TERMS AND CONDITIONS .
(Continued)
13. SCHEDULING OF RECEIPTS AND DELIVERIES (Continued)
13.1 Nomination Process. (Continued)
(5) the Service Requester is told by its
Transportation Service Provider that the
downstream Service Requester did not have the
market or submit the nomination.
This information should be imparted to the Service
Requester on the Scheduled Quantity document."
(e) Ranking of Service. NAESB 1.3.23: "Ranking should be
included in the list of data elements. Transportation
service providers should use service requester provided
rankings when making reductions during the scheduling
process when this does not conflict with tariff-based
rules."
13.2 Scheduling Process.
(a) Scheduling Priorities. The Quantity of Gas that Transporter
is obligated to deliver on any Day will be limited to the
Quantity of Gas received by Transporter for Shipper's
account on such Day as adjusted for fuel used and lost and
unaccounted-for gas. Scheduled deliveries by Transporter for
a Shipper will be subject to confirmation of scheduled
receipts by Transporter for Shipper's account, except as
provided in Section 13.2(b). Transporter will schedule
nominated Quantities in the following sequence: first, by
mainline capacity; and, second, by Receipt Points and
Delivery Points, as follows:
(1) Mainline Capacity. Mainline capacity will be
allocated in the priority and sequence described
below:
(i) To Shippers nominating Firm Transportation
Service.
If mainline capacity is constrained and
Transporter cannot accommodate the total
Quantities nominated, then available capacity
will be allocated as follows: