Kern River Gas Transmission Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 07/01/2000, Docket: RP00-288-000, Status: Effective
Original Sheet No. 123 Original Sheet No. 123 : Effective
GENERAL TERMS AND CONDITIONS
(Continued)
13. SCHEDULING OF RECEIPTS AND DELIVERIES (Continued)
13.1 Nomination Process. (Continued)
(iii) With respect to the processing of the requests for
decreases during the intraday nomination/confirmation
process, in the absence of agreement to the contrary,
the lesser of the confirmation quantities should be
the new confirmed quantity, but in any event no less
than the elapsed-prorated-scheduled quantity. If
there is no response to a Request For Confirmation or
an unsolicited Confirmation Response, the greater of
the confirmation quantity or the elapsed-prorated-
scheduled quantity should be the new confirmed
quantity.
(iv) With respect to 1.3.22 i, ii, and iii, if there is no
response to a request for confirmation or an
unsolicited confirmation response, the Transportation
Service Provider should provide the Service Requester
with the following information to explain why the
nomination failed, as applicable:
(1) the Service Requester's Transportation Service
Provider did not conduct the confirmation;
(2) the Service Requester is told by its
Transportation Service Provider that the
upstream confirming party did not conduct the
confirmation;
(3) the Service Requester is told by its
Transportation Service Provider that the
upstream Service Requester did not have the gas
or submit the nomination;
(4) the Service Requester is told by its
Transportation Service Provider that the
downstream confirming party did not conduct the
confirmation;