Kern River Gas Transmission Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 09/01/2005, Docket: RP05-456-000, Status: Effective
First Revised Sheet No. 122 First Revised Sheet No. 122 : Effective
Superseding: Original Sheet No. 122
GENERAL TERMS AND CONDITIONS
(Continued)
13. SCHEDULING OF RECEIPTS AND DELIVERIES (Continued)
13.1 Nomination Process. (Continued)
(d) Unconfirmed Nominations. NAESB WGQ 1.3.22:
(i) "With respect to the timely nomination/confirmation
process at a receipt or delivery point, in the absence
of agreement to the contrary, the lesser of the
confirmation quantities should be the confirmed
quantity. If there is no response to a Request For
Confirmation or an unsolicited Confirmation Response,
the lesser of the confirmation quantity or the
previously scheduled quantity should be the new
confirmed quantity.
(ii) With respect to the processing of requests for
increase during the intraday nomination/confirmation
process, in the absence of agreement to the contrary,
the lesser of the confirmation quantities should be
the new confirmed quantity. If there is no response
to a Request For Confirmation or an unsolicited
Confirmation Response, the previously scheduled
quantity should be the new confirmed quantity.