Kern River Gas Transmission Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/01/2002, Docket: RP02-482-000, Status: Effective
First Revised Sheet No. 116 First Revised Sheet No. 116 : Effective
Superseding: Original Sheet No. 116
GENERAL TERMS AND CONDITIONS
(Continued)
13. SCHEDULING OF RECEIPTS AND DELIVERIES (Continued)
13.1 Nomination Process.(Continued)
(c) Transporter sends quick response by noon (12:00
p.m. CCT);
(d) Transporter receives completed confirmations
from upstream and downstream connected parties
by 3:30 p.m. (CCT);
(e) Shipper and point operator receive scheduled
quantities by 4:30 p.m. (CCT on the day prior to
flow).
(ii) Evening Nomination Cycle:
(a) Nomination leaves control of nominating party by
6:00 p.m. (CCT);
(b) Nomination received by Transporter (including
from TTTSPs) by 6:15 p.m. (CCT);
(c) Transporter sends quick response by 6:30 p.m.
(CCT);
(d) Transporter receives completed confirmations
from upstream and downstream connected parties
by 9:00 p.m. (CCT);
(e) Transporter provides scheduled quantities to
affected Shippers, point operators and bumped
parties (notice to bumped parties) by 10:00 p.m.
(CCT on the day prior to flow).
Scheduled quantities resulting from an Evening
Nomination that does not cause another Service
Requester on the subject Transportation Service
Provider to receive notice that it is being bumped
should be effective at 9:00 a.m. on gas day; and when
an Evening Nomination causes another Service