Kern River Gas Transmission Company
Second Revised Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/2009, Docket: RP09-723-000, Status: Effective
First Revised Sheet No. 83 First Revised Sheet No. 83
Superseding: Original Sheet No. 83
. GENERAL TERMS AND CONDITIONS .
(Continued)
3. MEASURING EQUIPMENT (Continued)
3.6 Correction of Stated Metered Volumes. NAESB WGQ 2.3.14:
"Measurement data corrections should be processed within 6 months
of the production month with a 3 month rebuttal period. This
standard will not apply in the case of deliberate omission or
misrepresentation or mutual mistake of fact. Parties' other
statutory or contractual rights will not otherwise be diminished
by this standard."
3.7 Failure of Meters. In the event a meter is out of service or
registering inaccurately, the Volume of Gas delivered will be
determined:
(a) By correcting the error if the percentage of error is
ascertainable by calibration, tests or mathematical
calculation; or, in the absence of (a), then
(b) By estimating the Quantity of delivery by deliveries during
the periods under similar conditions when the meter was
registering accurately; or, in the absence of both (a) and
(b), then
(c) By using the registration of any check meter or meters if
installed and accurately registering.
3.8 Specific Gravity. The specific gravity of Gas flowing through the
meters will be determined by means of a gas chromatograph located
at Transporter's measuring station or at any other point on
Transporter's system.
3.9 Flowing Temperature. The flowing temperature of the Gas being
metered will be determined by means of a recording thermometer of
a type acceptable to both parties, installed and maintained in
accordance with the specifications set forth in the Gas
Measurement Committee Report No. 3, prepared by the Gas
Measurement Committee of the American Gas Association, dated
September, 1985, or any subsequent revision.