18.4 Reimbursement of Costs. Shipper shall reimburse
Transporter:
(a) For the costs of any facilities, other than
facilities included in Transporter's general system,
installed by Transporter with Shipper's consent to receive,
measure, transport or deliver natural gas for the account of
Shipper;
(b) For filing fees required in connection with
the Gas Transportation Contract(s) or a Park and Loan Service
Contract between Transporter and Shipper that Transporter is
obligated to pay to the FERC or any other governmental authority
having jurisdiction, exclusive of generally applicable regulatory
fees necessary for rendition of Transporter's service generally
to all customers; and
(c) For any and all occupation, sales tax, user
fee, or taxes or fees similar in nature or equivalent in
effect which are now or hereafter imposed or assessed against
Transporter by any lawful authority as a result of the
transportation of natural gas pursuant to the Gas
Transportation Contract(s) or the parking or loan of gas
pursuant to a Park and Loan Service Contract between Transporter
and Shipper, and which the Commission has determined, after a
Section 4 rate filing, to be directly assignable to the specific
service to be rendered by Transporter on behalf of Shipper
thereunder.
Any reimbursement due Transporter by Shipper
pursuant to this Section 18.4 shall be due and payable to
Transporter within ten (10) days of receipt by Shipper of
Transporter's invoice(s) for same. Transporter shall give
Shipper notice of any new or changed reimbursement under
Section 18.4(c) as soon as practicable after such new or
changed reimbursement becomes effective.
18.5 Shipper To Comply With All Terms. Transporter
shall not be required to render service on
behalf of any Shipper which on any day fails to comply with
any or all of the terms of the Gas Transportation Contract(s)
or a Park and Loan Service Contract, as applicable, between
Transporter and Shipper. Transporter may terminate
service prior to the expiration of a contract term only in
the event of nonpayment by Shipper in accordance with the
provisions of Section 14.4(c) of these General Terms and
Conditions or pursuant to the provisions of Sections 3.6 or 21.4
of these General Terms and Conditions.