Iroquois Gas Transmission System, L.P.
FIRST REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/1999, Docket: RP99-411-000, Status: Effective
Original Sheet No. 60B.01 Original Sheet No. 60B.01 : Effective
The Explicit Confirmation process requires that the Confirming
Party respond to a Request for Confirmation or initiate an
unsolicited Confirmation Response. Absent mutual agreement to
the contrary, Explicit Confirmation is the default methodology.
When a previously confirmed and scheduled quantity is altered,
notification of such alteration should be provided to all of the
below that are affected: 1) Confirmation Requester in a
Confirmation Response (or unsolicited Confirmation Response as
applicable) document by the Confirming Party; 2) Confirming Party
in a Request for Confirmation document by the Confirmation
Requester; 3) Shipper(s) in a Scheduled Quantity document by the
applicable Confirming Party or Confirmation Requester on whose
system the Shipper(s) nomination(s) were made.
Applicable notification(s) of such alterations should be
provided to the affected parties reasonably proximate in time
to the time during which the event causing the alteration was
acted upon by the Confirmation Requester or Confirming Party,
respectively. With respect to the implementation of this process
via the 1.4.x standards, Confirming Parties should send the
applicable document(s) to the applicable party(ies) no later than
the next time they are slated to communicate confirmations or
scheduled quantities (as applicable.)
When a Confirmation Requester receives a Confirmation Response
document from a Confirming Party by the conclusion of a given
quarter hour period, the Confirmation Requester will send to the
Confirming Party's designated site a corresponding Confirmation
Response Quick Response document by the conclusion of the
subsequent quarter hour period. The quarter hour periods will be
defined to begin on the hour and at 15, 30, and 45 minutes past
the hour. A given quarter hour will contain all transactions
whose receipt time is less than the beginning of the subsequent
quarter hour.
Confirming Parties' nightly processing and routine maintenance
occurring outside of normal business hours are apt to interrupt
the normal schedule of confirmations/quick response turnaround
stated above. Such delays should be kept to a minimum. The
normal schedule should be resumed at the earliest opportunity
and no later than the start of normal working hours the following
day, seven days per week.