Iroquois Gas Transmission System, L.P.
FIRST REVISED VOLUME NO. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 08/01/2009, Docket: RP09-739-000, Status: Effective
NINTH REVISED SHEET NO. 57 NINTH REVISED SHEET NO. 57
Superseding: EIGHTH REVISED SHEET NO. 57
3.8 Pre-qualification for Creditworthiness. Any
prospective bidder for capacity on Transporter's system may,
but is not required to, apply to establish creditworthiness
prior to submitting a bid for capacity. To pre-qualify, a
prospective bidder must submit to Transporter a request for
pre-qualification for creditworthiness that includes the
information specified in Section 3.4 of this Tariff.
Transporter will evaluate the prospective bidder's
creditworthiness in accordance with the provisions of Section
3 of this Tariff, advise the prospective bidder of the results
of its credit evaluation, and establish a list of all
pre-qualified bidders. To remain on this list, a prospective
bidder must update the information required by Section 3.4 of
this Tariff on an annual basis. Based on a subsequent review
of the prospective bidder's financial status, Transporter may
delete a pre-qualified bidder from its list of pre-qualified
bidders or may amend that list with respect to any limitations
on credit. All of the provisions of Section 3 of this Tariff
involving creditworthiness shall remain applicable to
prospective bidders who pre-qualify under this provision.
3.9 Creditworthiness Re-evaluation Timeline. In accordance
with NAESB WGQ Standard Number 0.3.9, after Transporter’s receipt
a Shipper’s/prospective bidder’s request for re-evaluation of its
creditworthiness (which request includes all required
information), Transporter shall provide a written response to the
Shipper’s/prospective bidder’s request within five (5) Business
Days. Such written response will include either a determination
of creditworthiness status, clearly stating the reason(s) for
Transporter’s decision, or an explanation supporting a future
date by which a re-evaluation determination will be made. In
no event shall such re-evaluation determination exceed twenty
(20) Business Days from the date of the receipt of the
Shipper’s/prospective bidder’s request unless Transporter and
its Shipper/prospective bidder mutually agree to a later date.
4. NOMINATIONS, ALLOCATING CAPACITY AND SCHEDULING
4.1 Nominations. The level of information required to
define a nomination is provided in NAESB WGQ Data Set 1.4.1
Version 1.8 (a pro forma nomination form is attached as
Sheet No. 188 to this Tariff), as required by the Commission
in 18 CFR 284.12(b)in accordance with Order 587 et al.
Iroquois shall provide upon request an indication of which data
elements it is using and what it is using them for.