Horizon Pipeline Company, L.L.C.
Original Volume No. 1
Contents / Previous / Next / Main Tariff Index
Effective Date: 10/12/2009, Docket: RP09-856-001, Status: Pending
Original Sheet No. 307 Original Sheet No. 307
EXHIBIT C [Negotiated Rate Agreement - ITS]
DATED ..........
EFFECTIVE ...............
Shipper: ...............
Contract No.: .............
ARTICLE 1
NEGOTIATED RATE PARAMETERS
1.1 Negotiated Rate Term: From.........Through.......... .
1.2 Negotiated Base Commodity Rate: $ .......... /Dth.
1.3 Eligible Transportation Quantity: .......... Dth./day.
1.4 Eligible Receipt Points: [as set forth in Exhibit A, unless otherwise listed herein]
ELIGIBLE POINT
NAME PIN MDQ (Dth/d.)
---- --- --------------
1.5 Eligible Delivery Points: [as set forth in Exhibit B, unless otherwise listed herein]
ELIGIBLE POINT
NAME PIN MDQ (Dth/d.)
---- --- --------------
ARTICLE 2
NEGOTIATED RATE TERMS AND CONDITIONS; OTHER CHARGES
2.1 General Negotiated Rate Limitations: The Negotiated Base Commodity Rate shall apply only to: (i)
service provided to Shipper by Horizon under the Transportation Agreement from the Eligible Receipt
Points to the Eligible Delivery Points during the Negotiated Rate Term; and (ii) an aggregate
maximum daily transportation quantity equal to the Eligible Transportation Quantity set forth in
Section 1.3 above, for all quantities transported under the Transportation Agreement. Unless
otherwise agreed, Shipper shall be charged all applicable additional rates, charges, and surcharges
set forth in Horizon's FERC Gas Tariff, as may be revised from time to time, for any aggregate
quantities transported on a daily basis for Shipper which: (i) are in excess of the Eligible
Transportation Quantity, or (ii) involve any receipt or delivery points which are not Eligible
Receipt or Delivery Points.
2.2 Discountable Third Party Surcharges: From time to time, certain commodity surcharges may be
approved by the FERC for inclusion in Horizon's FERC Gas Tariff which Horizon is: (i) required to
collect from Shipper and remit to the FERC or to another third party; and (ii) permitted to
discount the amount of such surcharge from the applicable maximum rate set forth in Horizon's FERC
Gas Tariff ("Discountable Third Party Surcharges"). [Describe any applicable surcharges covered by
this Section and whether Horizon is agreeable to negotiate the applicability of such surcharges as
part of the negotiated rates.]
2.3 Additional Rates, Charges, and Surcharges: In addition to the Negotiated Base Commodity Rates, and
unless otherwise expressly provided in this Agreement or agreed to in writing by Horizon, Shipper
shall also pay Horizon all other applicable maximum rates, charges, surcharges, and penalties of
any nature set forth in Horizon's FERC Gas Tariff, as may be revised from time to time, including
without limitation all applicable maximum: (i) Fuel and Gas Lost and Unaccounted For charges; (ii)
authorized and unauthorized overrun charges; (iii) commodity charges and surcharges; and (iv) ACA
surcharges.