Horizon Pipeline Company, L.L.C.

Original Volume No. 1

 Contents / Previous / Next / Main Tariff Index



Effective Date: 04/18/2002, Docket: CP00-129-001, Status: Effective

Original Sheet No. 122 Original Sheet No. 122 : Effective







efforts to accommodate such load pattern, and will consult with

Shipper in an effort to generally accommodate load variation to

the maximum extent feasible and compatible with the needs of

Shippers as a group. If, after written request by Horizon,

Shipper fails to restrict its hourly takes as specified herein,

Horizon may install and operate a load limiting device at any

Delivery Point where such failure has occurred. The cost for

such device, including the cost of installation, shall be paid

by Shipper within 30 days of its receipt of the bill therefor.




Unless otherwise described in an Agreement, the

Delivery Point(s) for transportation Agreements shall be

located at the interconnection between the facilities of

Shipper or its designee, and the facilities of Horizon.